footers…inspection…framing…inspection…decking…inspection
March 17th “J & V Patio” started, they moved and broke down the cement steps (they were not even attached to the house) and dug the holes for the footers (total of 14), now we have to wait for the inspectors to come out and measure.


While we wait for the township, the deliveries start…wood, cement, lattice, and deck hardware


March 21st, Inspection done! There was an extra footer hole that was needed but not on the plan submitted to the township. The paperwork will need to be updated and also kept on-site. But construction can begin!